Wiring and equipment shall comply with subpart S of this part. · The control circuit voltage shall not exceed 600 volts for a.c. or d.c. current. · The voltage at
According to 29 CFR 1910.179(g)(l)(i), all crane installations must comply with 29 CFR Part 1910 SubpartS, which contains grounding requirements in §§1910.304(g)(
As we enter into 2016, over 10 years have passed since the NEC code added the requirement for overhead cranes to have grounded power bar or festooning.
ANSIINFPA 70, National Electrical Code. If the hoist is installed as part of a total lifting system, such as an overhead crane or monorail, it is also the
OSHA requires annual inspections. They also require equipment be maintained on a scheduled basis, complete with dated records, according to the equipment duty
The portion of an overhead National Electrical Code 2020 of Minnesota > 6 Special Equipment > 668 Electrolytic Cells > 668.32 Cranes and Hoists · 610.13