ALWAYS LIFT BY USING LIFTING LOOPS OR. ANCHORS, IF AWAILABLE IN THE SLAB. VERIFY THE AMOUNT AND TYPE OF. LIFTING CLAMPS THAT ARE REQUIRED FOR. HEAVY SLABS.
We also have all necessary clamps and grips for emptying the casting beds of hollow core slabs. The lifting clamps are equipped with a lifting beam and two
A LIFTING DEVICE (A TRAVERSE WITH GRIPPERS) IS RECOMMENDED AND RENTED. UNDER A CONTRACT BY THE MANUFACTURER OF FLOOR SLABS. 2. Inspection of Production Items on
When using clamps, ensure that the clamp edges fit properly against sound concrete grooves insides of slab, after crane has taken load but before hoisting.
It consists os the following:Lifting beam with clamp supports adjustable along the length of the beam;Pair of clamps with opening and closing mechanism
It consists of the following:Lifting beam with adjustable clamp supports and safety pins;System to adjust the clamp's position along the lifting beam's
Lifting beam with Clamps is used for stripping out and stacking of pre-stressed hollow core slabs manufactured on casting beds with the help of Gantry crane.
It is absolutely necessary to lift the hollow core slabs near the ends of the slab as outlined in this brochure. Lifting the slabs too far away from the
Get contact details & address of companies manufacturing and supplying Precast Concrete Slabs, Precast Cc Slabs across India. quick to install on site with